Possible stage 2 load-shedding at short notice, warns Eskom

LOCAL

Stage 2 load-shedding may be implemented from Wednesday afternoon.

Eskom said the breakdowns of a generation unit each at the Majuba and Tutuka power stations and two at Kriel power station, have put a severe strain on the power generation system.

The power utility said it was also experiencing problems at some of its other plants.

“The delay in returning two generation units at Arnot, a unit each at Kusile and Hendrina power stations have exacerbated the electricity generation constraints,” Eskom said.

“We have 4,479 MW on planned maintenance, while another 12,951MW is unavailable due to breakdowns. We urge all South Africans to continue using electricity sparingly,” it said.

The power utility warned that stage 2 load-shedding may be implemented at short notice between 4pm and midnight should any further significant breakdowns occur.

Source: TimesLive

Picture of Tauhierah Salie
Tauhierah Salie

VOC became the first Muslim radio station in South Africa when a special events license was granted to the station in Ramadan/January 1995. Subsequent temporary broadcast licenses were granted, permitting the station to broadcast for 24 hours.

Donate to our Pledgeline
Listen on Online Radio Box! Voice of the Cape

Listen Live

Western Cape’s No.1 Community Radio Station